Structures Upgrade of Kitchener Wastewater Treatment Plant. Design Build Soil Anchors design to avoid the uplift effect due to high water table level.
Installing 2,000 soil anchors drilling in underwater sandy / gravel soils.
Mobilizing three machines using double casing drilling system and pressure grouting trough the temporary casing for soil anchors injection.